Client thread — Meridian scope
screenshot · Yesterday 18:02
Summary
- Meridian are asking whether 12 November still holds and want the DPA signed before go-live.
- They have asked to move CSV export into phase 1, described by them as small.
- They also need a named post-go-live point of contact for their ops team.
Action items0/4
Drafted reply
Hi Sandeep, Taking these in order: 1. 12 November still holds. 2. The DPA is with our legal team; we will have it signed well before go-live. 3. CSV export we can do, but it moves two days into the critical path — I would rather ship it in the first week after go-live than risk the date. Happy to do it in phase 1 if you would prefer the opposite trade. 4. Your ops team will have a named contact and an escalation address from day one; I will confirm the name tomorrow. Best,